OPTIMALISASI WAKTU DAN BIAYA PROYEK DENGAN METODE CPM, PERT, DAN CRASHING PROYEK LAPANGAN KONTAINER OLEH PT. SINAR CAKRA ABADI

Project planning requires supporting aspects so that errors do not occur such as increasing completion time. Delays occur from the influence of weather and workers' needs are not met. This research uses a container field project that takes 147 days. This project has a project time delay of 12 d...

Full description

Saved in:
Bibliographic Details
Main Author: Wendi Juliansyah, (Author)
Format: Book
Published: 2022-06-22.
Subjects:
Online Access:Link Metadata
Tags: Add Tag
No Tags, Be the first to tag this record!

Internet

Link Metadata

3rd Floor Main Library

Holdings details from 3rd Floor Main Library
Call Number: A1234.567
Copy 1 Available