OPTIMALISASI WAKTU DAN BIAYA PROYEK DENGAN METODE CPM, PERT, DAN CRASHING PROYEK LAPANGAN KONTAINER OLEH PT. SINAR CAKRA ABADI

Project planning requires supporting aspects so that errors do not occur such as increasing completion time. Delays occur from the influence of weather and workers' needs are not met. This research uses a container field project that takes 147 days. This project has a project time delay of 12 d...